Run a stakeholder interview

Talk to each person who will judge or fund a project, one at a time, about goals, constraints and what success looks like, and turn the answers into the inputs of a design brief.

Last reviewed

Outcome

A write-up of one conversation with one stakeholder: what they want the project to achieve, how they will judge it, the constraints they know about, what they believe about users and on what evidence, and what worries them. Across five to eight interviews, a summary of where stakeholders agree, where they conflict, and the open questions to settle before a design brief is signed.

When to use it

  • A project is starting and its sponsors, owners and neighbouring teams have not said what they expect in their own words.
  • A previous project stalled late because someone with a veto saw the work for the first time at the end.
  • You have joined a team or a client and need to learn the organisation's constraints before you design anything.

When not to use it

  • You want to know what customers do or need. Stakeholders' beliefs about users are hypotheses; interview users.
  • The decision is already made and the interviews would only collect approval. Say what was decided and ask for objections instead.
  • There is one stakeholder and you meet them every day. Write the brief with them directly: write a design brief.

Before you start

  • The list. Everyone who funds, approves, builds, sells, supports or will be measured on the result, with their role in the decision.
  • Background. Strategy documents, earlier research, metrics and any previous attempt at the project, read before the first call.
  • Time. Thirty to forty-five minutes per person, one person per conversation.
  • A guide. Eight to ten open questions, the same core set for everyone.
  • A notes template. One line per statement, marked as goal, measure, constraint, belief about users or concern.

Steps

Step 1: Map who to talk to and why

For each person on the list, write what they decide or influence and what they could block. Pick five to eight people that between them cover funding, approval, delivery and the customer-facing teams.

You should now have: a list of five to eight stakeholders, each with their role in the decision.

Step 2: Write one guide for everyone

Write the core questions: what does this project need to achieve for you? How will you know it worked? What has been tried before? What must not change? What do you hear from customers about this? What worries you? Add one or two questions specific to each role.

You should now have: a one-page guide with a shared core and role-specific additions.

Step 3: Book one person at a time

Invite each stakeholder separately, say how long it takes and what it is for, and that their answers will be summarised without attribution unless they agree otherwise. Group interviews let the most senior person set the answer.

You should now have: one-to-one sessions booked with every stakeholder on the list.

Step 4: Ask for goals and measures in their words

Start with what success means to them and how they will judge it. When an answer is general, such as "a better experience", ask what number or event would tell them it happened. Ask for examples of what has gone wrong before.

You should now have: each stakeholder's goal and measure of success, with examples.

Step 5: Ask what limits the work and what they believe about users

Ask about budget, deadlines, technical limits, legal or brand rules, and dependencies on other teams. Then ask what they believe users want and where that belief comes from: data, support tickets, a conversation, or a hunch.

You should now have: the constraints they know about and their beliefs about users, each with its source.

Step 6: Write it up the same day

Write the notes one statement per line, marked by type, with quotes kept verbatim. Note anything that contradicts another interview or the background documents.

You should now have: a written-up interview, one statement per line, with contradictions flagged.

Step 7: Summarise agreements, conflicts and open questions

After the last interview, sort the statements by type across everyone. Write where stakeholders agree, where their goals or measures conflict, and which beliefs about users have no evidence behind them. Send the summary to everyone interviewed and bring the conflicts to the brief meeting.

You should now have: a one-page summary of agreements, conflicts and unsupported beliefs, ready for the design brief.

Worked example

A bank starts redesigning how small businesses apply for an overdraft.

  1. The list has seven people: the product owner, the risk lead, the head of small-business sales, a support team lead, an engineering lead, a compliance officer and the marketing manager.
  2. Each gets the shared questions, plus one for risk about decline reasons and one for sales about what customers ask on calls.
  3. Seven separate thirty-minute calls are booked over a week.
  4. The product owner wants "more applications"; asked for a number, she says completed applications up 20%. The risk lead's measure is the share of approved overdrafts that default.
  5. Compliance says the affordability questions cannot be shortened. Sales believes customers abandon at document upload; asked where that comes from, they cite three calls.
  6. Each call is written up that afternoon. The product owner's and risk lead's measures pull in opposite directions; that is flagged.
  7. The summary lists four agreements, the conflicting measures, the fixed affordability questions and the unsupported belief about document upload, which goes into the research plan. The design brief meeting opens with the conflict.

Checklist

  • Every person who funds, approves, builds or supports the work is on the list.
  • Background documents were read before the first interview.
  • Every stakeholder was interviewed alone.
  • Each goal has a measure the stakeholder would accept.
  • Constraints and beliefs about users were recorded with their sources.
  • Interviews were written up the same day, one statement per line.
  • The summary names conflicts, not only agreements.
  • The summary went to everyone interviewed.

Common mistakes

  • Interviewing stakeholders as a group. The most senior voice decides, and the conflicts you need to find stay hidden.
  • Accepting goals without measures. "Better onboarding" cannot be signed off or checked later.
  • Treating beliefs about users as findings. A stakeholder's view of customers is a question for research, not an answer.
  • Pitching the design. Once you show ideas, the interview becomes a review of them.
  • Hiding conflicts in the summary. A brief signed over an unresolved conflict reopens it at the first design review.

Sources

  1. Buley, L. (2013). The User Experience Team of One: A Research and Design Survival Guide. Brooklyn: Rosenfeld Media.
  2. Portigal, S. (2013). Interviewing Users: How to Uncover Compelling Insights. Brooklyn: Rosenfeld Media.
  3. Nielsen Norman Group. Stakeholder Interviews 101.